Derrick Removal Case Study
13th March 2024
The Platform Operator are a long term client of DSL’s where we regularly complete asset integrity and drilling structure scopes.
The removal scope came from the Projects Team who knew that DSL had a comprehensive Track Record in removing drilling structures utilizing the
Floating Pole methodology, mitigating the need for costly HLVs.
CHALLENGES
- Completing a comprehensive Engineering
analysis to ensure structure Integrity is
maintained and proven throughout the
dismantling Phase. - Weather challenges and having enough fall-back
work to complete during WAH downtime. - Close Proximity of the Platform Flare to the
drilling structure
Work-scope
- Install dedicated Tuggers on the Drill floor
- Remove Derrick Ancillary Equipment Using Tuggers
- Assemble and Install Floating Pole in the Derrick
- Load Test Floating Pole Assembly
- Remove gin pole utilising Floating Pole Assembly
- Commence removal of Derrick sections utilising Floating Pole
Assembly from gin pole down to level 5 (top of derrick v-doors). - Removal and disassembly of Floating Pole Assembly
- Removal of Derrick Stem from Level 5 to Drill Floor utilising
Platform Crane. - Removal of all Drilling Equipment from the Drill floor